Manufacturing & quality

Three lines, one building, one test record.

Module assembly, rack integration and container build happen in the same facility in Ahmedabad. That is unusual in this market — and it is the reason a defect is caught at the module stage rather than at commissioning.

LocationAhmedabad, Gujarat
LinesModule · rack · container
Every blockFAT before dispatch

Facility

Designed around the test bench, not the showroom.

The layout follows the material: cells enter at goods-in and are graded before they are allowed onto the module line. A module does not move to rack integration without a signed record. A rack does not enter a container until insulation resistance and BMS communications have been verified.

Container integration sits on the same site as the rack line, which removes the transport leg where most handling damage happens. Blocks leave on a low-bed trailer with the FAT report travelling with them.

Under one roof

Module, rack and container integration, plus the FAT bench.

Handling

No rack leaves the site before it is inside a tested block.

Closure

Every unit has one owner from goods-in to handover.

Indicative floor plan: goods-in and cell grading, module line, rack assembly, container bay, test bench and dispatch. GOODS-IN cell grading MODULE LINE weld · seal · test RACK ASSEMBLY BMS · manifold CONTAINER BAY 12 racks · HVAC detection · FSS FAT BENCH capacity · RTE WAREHOUSE spares · cells DISPATCH low-bed
Fig. 06 — Material flow, indicativeNot to scale

Lines

What each line actually does.

Each line is a qualification boundary. Nothing crosses into the next line without a completed record from the last.

Line 01

Cell grading and module assembly

Incoming cells are graded on capacity, DCIR and open-circuit voltage before release. Modules are stacked, busbars laser-welded, fuses fitted and the cold plate bonded, then insulation-tested individually.

  • Cell grading and lot segregation
  • Laser welding with pull-test sampling
  • Module-level HiPot and OCV check

Line 02

Rack integration

Fifty-two modules go onto the rack in a fixed sequence, with the BMS harness, DC breaker and coolant manifold fitted and torqued to a controlled specification — audited, not assumed.

  • Torque audit on every power connection
  • Insulation resistance and continuity
  • BMS communications and firmware check

Line 03

Container integration

Twelve racks are installed in the 20-ft shell with HVAC, detection, suppression and deflagration venting. Coolant loop is pressure-tested and leak-checked before first energisation.

  • Rack alignment and DC bus assembly
  • Coolant pressure and leak test
  • Detection and suppression commissioning

Line 04

Factory acceptance test

Full charge and discharge at rated power, capacity and round-trip efficiency measured, thermal performance logged, protection functions proven and communications verified end to end.

  • Capacity and RTE measurement
  • Thermal and derating verification
  • Witnessed by the client or their adviser on request

Quality gates

Six gates between a cell and a handover.

A gate is a hold point with a named signatory and a record. If the record is incomplete, the unit does not advance — regardless of the delivery date.

Gate Stage What is checked Record
G1IncomingCell capacity, DCIR, OCV, dimensions, lot certificateCell lot release
G2ModuleWeld pull test, HiPot, OCV, mass, cold-plate bondModule record, serialised
G3RackTorque audit, insulation, BMS comms, firmware versionRack record
G4BlockHiPot, coolant pressure and leak, door and vent integrityBlock build record
G5FATCapacity, RTE, thermal, protection, commsFAT report
G6SiteCommissioning tests, grid compliance, punch list closureCommissioning report

Traceability

Every block can name its cells.

A serial number on the container is only useful if it resolves to something. Ours resolves to twelve racks, each rack to fifty-two modules, each module to its cell lot and test data — retained for the life of the asset.

That is what makes a warranty claim an engineering exercise rather than a negotiation.

Block

Serial, build date, FAT report, destination project.

Rack

Twelve rack serials per block, with BMS and test records.

Module

624 module serials per block, each with its HiPot and OCV data.

Cell lot

Supplier lot, grading results and incoming inspection record.

Capacity

How the facility scales.

Stated as a plan with gates, not a claim about today. Each phase starts only when the previous phase's qualification is closed.

Phase 1 · 2026

Module and rack

Module line and rack integration qualified. FAT bench operational. First dispatch to pilot projects.

Phase 2 · 2027

Container line

Container integration bay live. Block 5.0 in serial production with witnessed FAT as standard.

Phase 3 · 2028

Second shift

Second shift on module and rack lines; annual capacity approaching 1 GWh.

Target · 2030

5 GWh per year

Line expansion and domestic cell sourcing under evaluation to reach the 5 GWh target.

People & safety

High-voltage work needs trained hands.

Technicians working on energised DC systems are trained and authorised in writing for that voltage class, with refresher training on a fixed cycle. The same authorisation regime applies to our commissioning crews on site.

Production staff are trained on the specific equipment they operate, not a generic induction. Records are kept alongside the quality records for the units they built.

Authorisation

Written, per person, per voltage class, reviewed annually.

Training

Equipment-specific, with records retained by line and shift.

Emergency response

Drills for thermal events and DC isolation, run on a schedule.

Site crews

Same method-statement and permit discipline as the factory.

Factory visit

Come and see the line.

Serious buyers ask to witness a FAT. We would rather you did. Visits to the Ahmedabad facility can be arranged around a live test, so you see the equipment working rather than idle.